Builder extended contract

VCon Homes extended the contract. Here’s excerpt from their email: Commencement of your project: 05/11/2020Estimated contract date to finish: 27/08/2021New estimated finish date: 05/11/2021 The following time variations that have been added since construction commenced:* 2 Week Circuit Breaker* 4 Week Framing time extensionNew time variations that have been added:* Covid lockdown six restriction delays …

Mould detected during pre-plaster inspection

Darbecca conducted pre-plaster inspection on 2021-08-11. Excerpt from inspector’s report: What appears to be mould was noted to a web joist to the living area. I am not a mould specialist; therefore, I will not comment on the impact the observed mould (or material which appears to resemble mould) could have on the structure. I …

Concrete Poured

This morning (Tuesday, 22 December 2020) we discovered that the builders have poured the concrete. We are not happy because builders didn’t rectify the issues and didn’t tell us that they were going to pour concrete. Also, our consulting engineer identified that the bottom reinforcement at the back is exposed along with 50% of the …

Pre-slab Inspection

We hired a construction engineer to inspect the slab before the concrete is poured. Here is his report: The site inspection was carried out on Wednesday 9 December 2020. During the site inspection the proposed waffle slab layout was inspected. As part of the site inspection a number of photos were taken. The aim of …

Create your website with WordPress.com
Get started