VCon Homes extended the contract. Here’s excerpt from their email:
Commencement of your project: 05/11/2020
Estimated contract date to finish: 27/08/2021
New estimated finish date: 05/11/2021The following time variations that have been added since construction commenced:
* 2 Week Circuit Breaker
* 4 Week Framing time extension
New time variations that have been added:
* Covid lockdown six restriction delays is 2 weeks(based on ending 02/09/2021)
* Lock-up private inspection rectifications and response is 2 weeks
We called Consumer Affairs Victoria and they advised us that this kind of contract extension is not legally right.