Builder extended contract

VCon Homes extended the contract. Here’s excerpt from their email:

Commencement of your project: 05/11/2020
Estimated contract date to finish: 27/08/2021
New estimated finish date: 05/11/2021

The following time variations that have been added since construction commenced:
* 2 Week Circuit Breaker
* 4 Week Framing time extension
New time variations that have been added:
* Covid lockdown six restriction delays is 2 weeks(based on ending 02/09/2021)
* Lock-up private inspection rectifications and response is 2 weeks

We called Consumer Affairs Victoria and they advised us that this kind of contract extension is not legally right.

Advertisement

Published by Pavel Chuchuva

I help parents control YouTube videos for their children.

Leave a comment

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s