Concrete Poured

This morning (Tuesday, 22 December 2020) we discovered that the builders have poured the concrete.

We are not happy because builders didn’t rectify the issues and didn’t tell us that they were going to pour concrete.

Also, our consulting engineer identified that the bottom reinforcement at the back is exposed along with 50% of the bar chair:

This will corrode and there will be major issues developed. The contractor in now required to jack hammer concrete out at the rear and undertake rectification works. This was something I had raised during the site inspection. The works as they are do not comply with code requirements.

Published by Pavel Chuchuva

I help parents control YouTube videos for their children.

Leave a comment

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create your website with WordPress.com
Get started